KIPP Navigate | Phased DSA Site Upgrade and Modular Addition
Project Executive: Doug Giffin
Project Manager: Nicolas Romano
Project Sponsor:
KIPP Public Schools
School Operators:
KIPP Navigate (9-12)
Max Enrollment: 256 students
Construction Type: Portable classrooms
Project Delivery Method: Design-Bid-Build
Contractor: Swenson Builders
Architect: McKim Design Group
Size: 8,160 SF on an existing school campus
Status: Completed summer 2023
Total Project Cost:
$4.4M ($538/SF) hard and soft cost
Campus was brought in to manage the completion of a campus expansion program for the KIPP Navigate campus. The school ultimately needed eight new portable classrooms, four of which were on-site on a temporary basis.
Campus identified that the full project could not be completed in a single summer and worked with KIPP to break the project up into two phases that would minimize the risk to the school of buildings not being available at the start of school.