Aspire Vanguard | Conversion and Acoustic Separation

Project Executive: Doug Giffin

Project Manager: Nicolas Romano

Project Sponsor: Aspire Public Schools

School Operators:  Aspire Public Schools (TK-8)

Max Enrollment: 256 students

Construction Type: Conversion of health club space

Project Delivery Method: Design Build MEP

Contractor: Jose Jimenez

Architect: Artik Art & Architecture

Structural: Peoples Associates

Size: 12,448 SF on an existing school campus

Status: Completed fall 2022

Total Project Cost: 

$3.4M ($269/SF) hard and soft costs

Campus managed all aspects of the project development including design, entitlement, and construction.   Campus took over the last phase of a multi-phase project and needed to integrate design and construction with the previous phases.

 

Campus worked closely with the design team to create an acoustic separation of the lower level from the upper levels to address deficiencies from the prior phase.