Aspire Richmond Technology Academy | Office Conversion + New Construction

Project Executive: Doug Giffin

Project Manager: Nicolas Romano

Project Sponsor: 

Steve and Susan Chamberlin

School Operators: 

Aspire Public Schools RTA (TK-5)

Max Enrollment: 640 students

Construction Type: Renovation & new masonry building

Project Delivery Method: Design Build MEP

Contractor: Kaufman Construction

Architect: Studio Bondy Architecture

Structural Engineer: Fratessa Forbes & Wong

Size: Conversion | 39,045 SF

New Construction | 15,300 SF

Status: Completed with phased delivery in 2018 and 2019

Total Project Cost: 

$24.2M ($443/SF) existing building, hard, and soft costs

Campus managed all aspects of the project development including acquisition, design, entitlement, and construction of renovation of an existing bank building and addition of a single-story classroom and multi-purpose building.  Entitlements were phased to navigate a challenging entitlement environment. 

 

Campus identified a site that allowed schools by right and pushed through approval of the original work and occupancy with only a building permit.  Subsequent phases were later entitled with the support of the existing school community.